Testing the Plan

Evaluating the plan for accuracy and completeness 

    + Expectations for business units to demonstrate ability to achieve objectives within metrics specified in BIA (RTO,RPO,RSL)

    + Degree of testing to be accomplished.

    + Roles and Responsibilities.

    + Testing of internal and external dependencies.

    + Justification for testing strategy.

    + Objectives should be measurable with clear expectations defined.

    + Testing strategy should be reviewed and approved by senior management.


Types of BCDR Tests

1. Checklist Test

    + copies of plan distributed to different department.

    + Functional managers review.

2.Structured walk-Through (Table-Top) test

    + Representatives from each department go over the plan.

3.Simulation test 

    + Going through a disaster scenario.

    + Continues up to the actual relocation to an offsite facility. 

4.Parallel Test

    + Systems moved to alternate site and processing takes place there.

5.Full-Interruption test

    + Original site shut down.

    + All of processing moved to offsite facility.